Planning a fence installation: holes, access and equipment
Count the holes, read the plan, measure the route. Then pick the auger.
Start with the plan, not the machine
Three numbers decide the rental: how many holes, how wide, how deep.
- Your fence plan, your post size and your local building department set the hole diameter and depth. A fence that needs a permit will have those numbers on the approved drawings. A fence that does not still needs a footing below the frost line if you want the posts to stay put through a Michigan winter, and the frost line in most of southeast Michigan is about 42 in. Treat that as general guidance and confirm the required depth with your township before you book.
- Once you have diameter and depth, count the holes. Corner posts, gate posts and end posts are usually larger than line posts, so you may need two bit sizes. Write down the count for each size. That list is what the counter staff uses to match a bit to a machine, and it tells you whether a one-person auger is realistic or whether a loader-mounted auger is the right starting point.
- Then walk the fence line with a probe or a shovel. Sand drills fast. Clay drills slowly and holds the bit. Fieldstone, old roots and buried concrete stop a handheld auger and slow a hydraulic one. What you find at 2 ft is more useful than what you see on the surface.
Which auger fits which fence
- The Little Beaver is a one-person gas auger with 6, 8 and 10 in bits. Its engine sits apart from the drill head on a torque tube, so the twisting force does not go through your arms. It fits a short run of holes in workable soil where nothing bigger can get in, and it rides in a pickup. A long run, clay, rock or a bit larger than 10 in pushes you to a hydraulic auger on a machine.
- The MT100 stand-on loader with a hydraulic auger is 35.6 in wide at the machine body and is the pick for a fenced backyard with a standard gate. The T66-2 tracked loader with auger has more torque, takes bits up to 36 in and drills to 72 in without an extension, so it leads on long runs, clay and large gate-post holes when the route is open. On pavement or a firm gravel lot the wheeled S570 with auger does the same work and is quicker on hard surfaces; it ruts turf. Confirm bit sizes for the machine you choose at booking. The first bit is included with every auger rental; additional bits are added at booking.
- Posts set in concrete need a mixer or bagged mix at every hole. The towable concrete mixer holds 1.5 to 2 bags per batch, which suits post setting and small footings. Rinse it after the last batch.
Before anyone drills
- Contact MISS DIG 811 at least three business days before augering. It is free and required by Michigan law. MISS DIG marks public utilities only. Irrigation, landscape lighting, invisible fence and a line from the house to a shed or pole barn are private and will not be marked, so use your own records or a private locator for those.
- Confirm the property line before you set a corner post on it. A rental metal detector helps you find existing survey pins and buried metal, and finding one is a useful clue. Finding metal does not establish a legal boundary; a surveyor does. Our guide on looking for property pins covers what the detector can and cannot tell you.
Check the route before you pick a size.
An auger on a machine is only useful if the machine reaches the fence line.
Measure the clear opening
Gate fully open, latch to post, at the narrowest point. The MT100 body is 35.6 in wide; the auger head and bit hang below the arms and the bit can be wider than the machine. Measure the route, not the nominal gate size.
Walk the fence line
Look for slopes, soft ground, septic fields, irrigation heads and low branches. Tracks spread weight; they do not prevent all lawn damage, and saturated ground is not workable after a hard rain. Give it a day.
Know your numbers
Bring hole count by size, diameter and depth from the plan, and what the soil is like at depth. Those three decide the machine and the bits.
Auger carrier widths, from our product pages
Width is the machine body. The auger bit and drive head add to it, and a 36 in bit is wider than the MT100. If you are a few inches short at a gate, pulling one fence panel is often easier than drilling a full run with a smaller machine.
Little Beaver handheld auger — one person, walks through any gate
Bobcat MT100 stand-on loader with auger — 35.6 in
Bobcat T66-2 track loader with auger — 67 in
Bobcat S570 wheeled loader with auger — 68 in with bucket
Before ground disturbance: — arrange utility locating through MISS DIG 811 at least three business days ahead, and locate private lines yourself. Review site hazards with our team.
Your fence planning checklist
Save these details before you request equipment.
- Hole count by size (line, corner, gate and end posts)
- Hole diameter and depth from the approved plan or building department
- Soil at depth: sand, clay, rock, roots
- Narrowest clear opening on the route, gate fully open
- MISS DIG 811 ticket date and private lines you know about
- Property line confirmed, pins found or survey in hand
- Concrete plan: bags per hole, mixer or pre-mixed
- Delivery location and preferred dates
Let's match the machine to your job.
Tell us what you're working on. Our Hamburg team serves Southeast Michigan, seven days a week.
(810) 231-7368
Explore equipment for this guide
Questions before you rent
What size auger bit do I need for fence posts?
Your plan sets it, not the rental counter. The hole has to be wide enough for the post plus the concrete collar your plan or your fence supplier calls for, and deep enough to reach below the frost line, about 42 in in most of southeast Michigan. Take the diameter from the plan and match it to the bit list for the machine you book. The Little Beaver takes 6, 8 and 10 in bits; the loader-mounted augers take larger sizes, and we confirm the exact bit list for each machine at booking. The first bit is included.
Do I need to call MISS DIG for fence posts?
Yes. Augering is excavation under Michigan law. Contact MISS DIG 811 at least three business days before you drill; the service is free. MISS DIG marks public utilities only. Irrigation lines, invisible fence, landscape lighting and a private line to a shed are not marked, so check your own records or hire a private locator. A metal detector helps you look for buried metal but does not replace the locate.
Can the auger get into my backyard?
The Little Beaver walks through any gate with one person. The MT100 with auger is 35.6 in wide at the body and is built for standard 36 in gates, but the bit and drive head can be wider than the machine, so measure the clear opening with the gate fully open and walk the route. The T66-2 and S570 need a clear 6 ft. If you are a few inches short, removing one fence panel is often easier than running the job on a smaller machine.
Clay or rocky soil: which auger?
Clay holds the bit and rock stops it, and both wear out a one-person auger crew fast. A hydraulic auger on the MT100 or T66-2 keeps turning through clay and works around fieldstone that a handheld unit will fight. If you hit buried concrete or a large stone that the bit will not pass, that hole becomes a digging job rather than a drilling job; the E10 excavator handles that in tight access. Tell us what you find when you probe the line and we will match the machine.
Should I tow the auger or have it delivered?
The Little Beaver fits in a pickup. The MT100 with auger rides on our 12 ft ramp trailer with a 2 in ball, which a half-ton pickup typically handles; we confirm the setup at the counter. The T66-2 and S570 ride on the 16 ft equipment trailer with a 2 5/16 in ball and need a 3/4-ton truck or larger. Delivery runs seven days a week on our trucks, priced by drive time from Hamburg: $85 round trip within 45 minutes for truck and trailer loads, $125 at 46 to 75 minutes, and a quote beyond that. The fee is confirmed at checkout.
How long should I rent the auger for?
You pay for the time it is out, including weekends, not the hours on the meter, and there is no hour cap. Rental periods run 1 to 4 hours, 4.5 to 24 hours, one week (which covers 3 to 7 days) and four weeks. A fence usually spans drilling, setting posts, letting concrete cure and hanging panels, so most customers take the auger for a day and return it before the concrete work starts. Keep it longer and the extra time is prorated, never more than the next full period.