Planning a French drain: route, outlet and excavation equipment
Find the outlet, lay out the route, pick the trencher or excavator, then dig.
A French drain in five stages
The digging is the short part. Most of the work that decides whether the drain lasts happens before the machine arrives.
The week rate covers 3 to 7 days. A drain that needs a weekend plus a weekday for backfill often fits that period. Rental time is the time the machine is out, with unlimited run hours and fuel at our cost.
Find where the water will go
A French drain is a gravity pipe. It needs a discharge point lower than the lowest part of the trench: a ditch, a swale, a storm inlet, daylight on a slope, or a dry well where the soil drains. Stand at the wet spot and at the proposed outlet and measure the drop between them with a line level or a laser. If the drop is near zero, or the only low point is a neighbor's yard, stop and rethink. Also confirm the outlet is one you are allowed to use; some townships restrict discharge to the street or storm system.
No machine yet. A line level, stakes, string and a tape measure.
Lay out the run and mark utilities
Paint or flag the route from the wet area to the outlet. Keep it as straight as the yard allows. Note every obstacle: tree roots, septic tank and field, irrigation lines, the sidewalk, a fence. Contact MISS DIG 811 at least three business days before you dig; it is free and required by Michigan law. MISS DIG marks public utilities, not private lines such as irrigation, landscape lighting, invisible fence or a line to an outbuilding. Use your own records or a private locator for those. A rental metal detector helps you look for buried metal but does not replace the locate.
Metal detector for finding old pins and buried metal along the route.
Choose the trencher or the excavator
The Ditch Witch C24X trencher cuts a 6 in wide slot up to 36 in deep and is 35.8 in wide, so it passes most 36 in gates when the attachment and the turn allow it. It suits a straight run in soil without large rock or roots, and it leaves a neat trench with the spoil beside it. If your pipe plus stone bedding needs more than 6 in of width, if the trench goes deeper than 36 in, or if the route crosses roots, fieldstone or old concrete, the dig is excavator work. The Bobcat E10 retracts to 28 in for doorway and tight-gate access and digs about 6 ft. The E35 is the usual pick with open access, digs about 10 ft and places spoil where you want it, including into a trailer.
Trencher 6 in x 36 in, Bobcat E10, or Bobcat E35 with a narrow bucket.
Cut to grade, bed, pipe, wrap
Dig from the outlet back toward the wet area so water in the trench drains away as you go. Check the fall as you cut; a trench that dips holds water in the pipe. Follow the pipe manufacturer and your local building department for depth, stone and fabric. The trencher stops at 36 in, so anything that must reach frost depth (about 42 in in most of southeast Michigan) is an excavator trench. Dig depths are maximums at the bucket pin. If anyone will stand in the trench, slope or shore it; trench walls collapse without warning.
The same machine from stage 03. A tracked buggy or the MT100 moves stone through a gate if the pile is on the driveway.
Backfill, compact and restore
Backfill in lifts of a few inches and compact each one, or the trench line will settle into a visible dip after the first winter. In a 6 in trencher cut, that is a hand tamper. In a wider excavator trench, the plate compactor fits once the pipe is covered. Keep spoil off the lawn you want to keep, or put it on plywood. Haul the extra in the 7x14 dump trailer; wet clay is heavy and fills the weight limit long before the box looks full.
Plate compactor; 7x14 dump trailer or 5x10 utility trailer for spoil.
What a finished drain looks like
- A working French drain disappears. The lawn over it is level, the outlet runs during a rain and stops a few hours after, and the spot that used to pond is dry by the next morning. The trench line should not show as a dip or a strip of lighter grass, which is why the backfill stage matters as much as the dig.
- Check it during the first few heavy rains. Water at the outlet means the drain is collecting. No water at the outlet with the yard still wet means the trench did not reach the water, the fall is wrong, or the pipe is blocked. Fix it while the sod is still easy to lift.
Mistakes we see on return
- The most common one is digging first and looking for the outlet second. The second is a trench that follows the surface of a lawn that is not flat, so the pipe has a hump in it. The third is a drain that collects roof water from a downspout as well as groundwater, which overloads it in a storm; extend the downspout separately and let the French drain handle the ground.
- On the equipment side, the usual misses are booking a trencher for a route full of maple roots, and booking the E35 for a yard with a 36 in gate. Walk the route and measure the opening before you call.
When this is a contractor's job
- Water in the basement, a footing drain around the foundation, a whole-yard system with multiple lines, or a drain that has to cross a septic field or tie into a public storm system. Those need design, sometimes permits, and someone who carries the liability. Ward's rents the trencher and excavators to contractors every week; if yours wants to pick up the machine for your job, send them our way.
Before you book, check the site.
Measure the narrowest opening
Trencher 35.8 in, E10 28 in retracted and 43 in extended, E35 69.7 in. Measure the clear opening with the gate fully open and include latches, posts and the turn into it. The E10's extended width is what it needs to work stable.
Walk the route
Drainage work happens on wet ground. Tracks spread weight but do not stop rutting on a saturated lawn. After a hard rain, give it a day. Note septic fields, irrigation heads and sprinkler lines.
Bring the numbers
Run length, depth at the deepest point, the drop from start to outlet, and the trench width your pipe and bedding need. These decide trencher versus excavator.
Machine widths, from our product pages
Width is the machine body. The E10 needs its 43 in working width once it is through the opening. If you are a few inches short, pulling one fence panel is often easier than running the job on the wrong machine.
Bobcat E10 mini excavator — 28 in retracted / 43 in extended
Trencher 6 in x 36 in — 35.8 in
Bobcat MT100 stand-on loader — 35.6 in
Bobcat E35 mini excavator — 69.7 in
Before ground disturbance: — contact MISS DIG 811 at least three business days before digging or trenching. Free and required by Michigan law. It does not mark private lines.
Your French drain checklist
Save these details before you request equipment.
- Outlet location and the measured drop from the wet area to it
- Permission to discharge at that outlet (township, HOA, neighbor)
- Route marked; roots, rock, septic and irrigation noted
- Trench width and depth from your pipe and stone spec
- Narrowest access point and turning space
- Where spoil goes and where stone will be dropped
- MISS DIG 811 ticket date
- Delivery location and preferred dates
Let's match the machine to your job.
Tell us what you're working on. Our Hamburg team serves Southeast Michigan, seven days a week.
(810) 231-7368
Explore equipment for this guide
Questions before you rent
Is the trencher wide enough for a French drain?
It cuts 6 in wide. Whether that is enough depends on the pipe diameter and how much stone your spec calls for around it. Many residential drains use a small-diameter perforated pipe and fit, and some specs call for more stone than a 6 in slot allows. Check the pipe maker's recommendation and your local building department before you book. If you need wider, the E10 with its 8 in bucket or the E35 with a 12 in bucket digs it.
How deep should the trench be?
That comes from the pipe manufacturer and the local building department, not from us, and it depends on what the drain is for. The trencher reaches 36 in. Frost depth in most of southeast Michigan is about 42 in, which matters for a water line but usually not for a yard drain. If the spec takes you past 36 in, it is an excavator trench. Any trench a person stands in needs to be sloped or shored; dig depths listed for our machines are maximums at the bucket pin.
Will the machine get into my backyard?
The trencher is 35.8 in wide and the E10 retracts to 28 in, so either can pass a 36 in clear opening when the route and the turn allow it. The E10 then widens to 43 in to work. The E35 is 69.7 in and needs a clear 6 ft. Measure the opening with the gate fully open, including the latch, and walk the path for slopes, soft ground and sprinkler heads. Our backyard access guide covers this in detail.
How do I get the stone to the trench?
If the stone pile is on the driveway and the trench is in the back, something has to carry it. The Bobcat MT100 stand-on loader is 35.6 in wide and carries a bucket at a time through a 36 in opening. The Canycom tracked buggy is 35 in wide and carries a load without a bucket to operate, which suits a slope or a first-time operator. With open access, the E35 bucket or a full-size loader moves stone faster. Tell us the quantity and the route and we will suggest the combination.
What about delivery and towing?
The trencher rides on the 5x10 utility trailer with a 2 in ball. The E10 and E35 ride on the 16 ft equipment trailer with a 2 5/16 in ball; the E35 needs a 3/4-ton truck or larger, and your tow rating has to cover trailer plus machine plus attachments. Delivery is seven days a week on our trucks, priced by drive time from Hamburg: $85 round trip within 45 minutes for a trencher or excavator load, $125 at 46 to 75 minutes, and a quote beyond that. The fee is confirmed at checkout.