Planning deck footing excavation around an existing house

Footings next to a foundation, through a side yard, to a depth your plan sets. Here is the order of work.

Deck footings next to a house, in order

The plan tells you where and how deep. The site tells you what gets there.

If the plan shows footings deeper than the E10 reaches, a continuous footing, or anything that touches the existing foundation, call us before you book. That may be an E35 job with a 6 ft route, or it may be a job for a contractor.

Pull footing size, depth and layout from the approved drawings

Your permit set lists footing diameter, depth and spacing. Depth has to reach below the frost line, about 42 in in most of southeast Michigan, and your building department sets the actual number. Ask them whether they inspect the open hole before concrete goes in; that decides your schedule. Lay out the footings with string lines off the house and mark each center.

Tape, string, marking paint. No rental yet.

MISS DIG, private lines and the foundation itself

Contact MISS DIG 811 at least three business days before digging; it is free and required by Michigan law. Around a house, the lines MISS DIG does not mark are the ones you will hit: the water or electric line to a shed, irrigation, landscape lighting, a downspout drain. Walk them yourself. A metal detector helps you find buried metal before you dig, and it does not replace the locate. Note where the foundation footing is likely to extend past the wall so you keep the hole off it.

Metal detector for checking the footing locations for buried metal.

Measure the side yard and the route

Most decks sit behind a house with one way in. Measure the clear opening at the gate and the narrowest point between the house and the fence, and check for air-conditioning units, window wells, meters and downspouts on the route. Tracks spread weight; they do not prevent all lawn damage, and a saturated yard is not workable after a hard rain. Plywood over soft spots helps.

Decides between the Little Beaver, the MT100 with auger (35.6 in body) and the E10 (28 in retracted).

Auger the holes, or dig them with the E10

In workable soil with a round footing, an auger is the fast way: the Little Beaver for a few holes at 6 to 10 in, the MT100 with hydraulic auger for more holes or larger bits through a standard gate. When the plan calls for a wider footing, a bell or square form, or when the probe finds roots, fieldstone or old concrete, the E10 excavator digs the hole instead. It retracts to 28 in to pass a gate or doorway and digs about 6 ft at the pin. Keep the hole off the existing foundation footing; digging below it is a job for a professional.

Little Beaver, MT100 with auger, or Bobcat E10 with 8 or 15 in bucket.

Square the bottoms, check depth, call the inspector

Clean loose soil from the bottom of every hole and measure depth from finished grade, not from the top of the spoil pile. Keep water out if rain is coming. If your township inspects open holes, schedule it now and keep the holes covered until the inspector has signed off. Then set your forms or tubes to the height the plan calls for.

Hand tools. A submersible utility pump if holes take on water.

Mix and place the footings

A towable concrete mixer holds 1.5 to 2 bags per batch, which suits footings and post bases where a ready-mix truck cannot reach or the volume is too small to order. Set anchors or post bases while the concrete is wet, per the plan. Rinse the drum right after the last batch. Backfill around the forms once the concrete has set up and haul the spoil you do not need.

Concrete mixer. A 5x10 utility trailer or 7x14 dump trailer for spoil, watching weight.

Auger or excavator for deck footings

  • An auger drills a round hole the size of the bit and lifts the spoil out on the flights. That is exactly what a pier footing in loam or sand wants. The Little Beaver covers 6, 8 and 10 in holes with one person. The MT100 with hydraulic auger takes larger bits, drills faster and still passes a standard gate at 35.6 in; confirm its bit sizes at booking, and the first bit is included.
  • An excavator digs whatever shape you need and handles what an auger cannot: roots from a tree that used to stand there, fieldstone, the concrete from an old deck, or a footing wider than any bit. The E10 is the one that fits the side yard, retracting to 28 in and digging about 6 ft at the pin. If a 6 ft route is open to the back of the house, the E35 digs faster and loads a trailer, and our mini excavator depth guide compares the two.
  • What changes the answer: a plan that calls for a belled or square footing (excavator), a count high enough that hand-lifting a handheld auger wears out the crew (MT100 auger), or a route under 28 in clear (hand digging, or pull a fence panel).

Mistakes we see on deck footings

  • Measuring depth from the spoil pile instead of finished grade, so the footing ends up shallower than the plan. Drilling before the MISS DIG ticket clears. Setting a footing on the existing house footing, or undermining it, instead of keeping the hole clear of it. Booking an auger for soil nobody probed, then finding fieldstone at 2 ft.
  • Renting the machine for the wrong day is the other one. Footings are a short dig and a long wait: locate, dig, inspect, pour, cure. Rent the auger or E10 for the dig day and the mixer for the pour day, rather than paying for either to sit.

The side yard decides the machine.

Measure the clear opening

Gate fully open, latch to post, plus the narrowest point between the house and the fence. The E10 retracts to 28 in; the MT100 body is 35.6 in and its auger can be wider than the machine.

Walk the route

Air-conditioning units, meters, window wells, downspouts and irrigation heads live along the side of a house. Mark anything the tracks would cross or the counterweight would swing into.

Know the depth

Bring footing diameter, depth and count from the approved plan. The E10 digs about 6 ft at the pin; practical depth is less.

Before ground disturbance: — arrange utility locating through MISS DIG 811 at least three business days ahead, locate private lines yourself, and keep every hole clear of the existing foundation. Review site hazards with our team.

Your deck footing checklist

Save these details before you request equipment.

  • Footing diameter, depth and count from the approved plan
  • Inspection requirement and timing from the building department
  • MISS DIG 811 ticket date and private lines marked
  • Clear opening at the gate and narrowest point along the house
  • Soil at 2 ft at two or three footing locations
  • Concrete volume and whether a mixer or ready-mix fits the job
  • Where spoil goes and how it leaves the site
  • Delivery location and preferred dates

Let's match the machine to your job.

Tell us what you're working on. Our Hamburg team serves Southeast Michigan, seven days a week.

(810) 231-7368

Explore equipment for this guide

Questions before you rent

How deep do deck footings need to be?

Deep enough to bear below the frost line, which is about 42 in in most of southeast Michigan, and your local building department sets the number you have to hit. Your approved plan will show it along with the footing diameter. We do not set depths at the rental counter; we match a bit or a bucket to the depth and diameter you bring us. Measure depth from finished grade, and ask your township whether they inspect the open hole before you pour.

Can an excavator get down the side of my house?

The Bobcat E10 is built for it. Its undercarriage retracts to 28 in to pass a standard gate or doorway and extends to 43 in for stability once it is through. Measure the clear opening with the gate fully open and the narrowest point between the house and the fence, and look for air-conditioning units, meters and window wells on the route. The E35 needs a clear 6 ft. Width is half of it; the turn into the opening and what the tracks cross are the other half.

Should I auger the footings or dig them?

Auger them when the plan calls for a round pier in soil that lets a bit work: the Little Beaver for a few 6 to 10 in holes, the MT100 with hydraulic auger for more holes or larger bits through a 36 in gate. Dig them with the E10 when the footing is wider than a bit, belled or square, or when the ground has roots, fieldstone or old concrete in it. Probe two or three footing locations to 2 ft before you decide. The first bit or bucket is included either way.

Do I need a concrete mixer or should I order ready-mix?

A handful of pier footings is usually too small an order for a ready-mix truck and too much to mix in a wheelbarrow. The towable concrete mixer holds 1.5 to 2 bags per batch and tows on a 2 in ball. If the footing count or size pushes the volume up, or a truck can reach the back of the house, ready-mix may make more sense; count your bags first. Rinse the drum right after the last batch.

How many days do I need the machine?

Footings are a short dig and a long wait. Most customers rent the auger or E10 for a single day, dig every hole, then return it before inspection and the pour. The mixer comes back on pour day. You pay for the time each item is out, including weekends, with unlimited run hours; periods run 1 to 4 hours, 4.5 to 24 hours, one week (which covers 3 to 7 days) and four weeks. Keep something longer and the extra time is prorated, never more than the next full period.