Project walkthrough

Planning equipment for a detached garage build

Six phases, one machine family per phase. Rent each one for the days that phase runs, not for the whole build.

Why the order matters

Every phase leaves the site different for the next machine. The loader needs the footprint clear. The excavator needs the pad graded so the footing depths are measured from a known surface. The telehandler needs a firm staging spot that was decided before the footing spoil got piled on it. The boom lift needs outrigger pads on ground that was not just backfilled. If you book machines by phase and walk the site before each delivery, each one arrives to a lot that is ready for it.

The two things that most often stall a garage build are the utility locate and the ground. Contact MISS DIG 811 at least three business days before any digging, trenching or augering; it is free and required by Michigan law, and it does not mark private lines such as the run from the house to an existing shed or a landscape lighting circuit. For the ground, tracks spread weight and reduce rutting, but they do not make saturated ground workable. After a hard rain, give it a day before the loader or the telehandler arrives.

A detached garage, phase by phase

Each phase uses a different machine for a few days. Book them in sequence so nothing sits idle on the lot.

The week rate covers 3 to 7 days, so a phase that runs Thursday through the weekend is one week rental. Attachments rented with a Ward's skid steer are half price, which makes the grapple and soil conditioner cheap additions to the loader days. Fuel is billed at our cost.

Clear and rough-grade the pad

Strip sod and topsoil from the footprint plus a working margin, pull any brush or small stumps, and rough-grade so the slab area drains away from the house. A tracked loader does the stripping and grading; the 66 in root grapple handles brush and roots without carrying soil to the pile. Stockpile topsoil where it will not block the material trucks; you will want it back for final grade.

Bobcat T66-2 or Kubota SVL65-2 with bucket; 66 in root grapple for brush; 7x14 dump trailer to haul spoil

Dig footings and the utility trench

Footings go to the depth your building department requires; the frost line in most of southeast Michigan is about 42 in, so plan on a trench a person may have to enter. Slope or shore anything a person stands in. The E35 digs the footing trench and places spoil beside it or in the dump trailer, and its dozer blade backfills later. The electric feed from the house can go in with the trencher if your required burial depth is within its 36 in limit; otherwise the excavator digs that run too.

Bobcat E35 (E48 if you need more reach and lift); Ditch Witch trencher for a shallow conduit run

Compact the base and pour the floor

Spread stone in lifts and compact each one. The plate compactor handles a garage pad; the 36 in ride-on roller is quicker on a large pad or the apron. If the ready-mix truck cannot back to the forms, the Canycom tracked buggy carries 2,200 lb per trip across lawn or soft ground; the wheeled buggy wants firm, level ground. Cut control joints with the early-entry saw within hours of finishing, before the slab cracks on its own.

Plate compactor or 36 in ride-on roller; Canycom tracked buggy; concrete mixer for footings and small pours; early-entry saw

Stock the deck and set the trusses

A one-story garage is within the SkyTrak 6034's 34 ft lift and 23 ft forward reach, and the compact machine suits a residential lot. Use forks to land lumber and sheathing units, then the 15 ft truss boom to hang each truss and set it over the wall. The truss boom hook is rated 2,000 lb, and the extension reduces the machine's capacity; read the chart in the cab for the reach you will actually use. Tag lines keep the truss from spinning. Operators must be trained.

SkyTrak 6034 telehandler with forks and truss boom (6042 if the set point is farther than the 6034 reaches)

Get people and material to the eave

Roofing bundles go up on the telehandler forks while it is still on site. For the people, a towable 45 ft boom reaches a garage eave from the driveway with outriggers set on firm ground or pads. A 32 ft extension ladder covers a quick task; a Bil-Jax tower suits hours of siding in one spot. The 10 ft 6 in aluminum brake bends trim coil for fascia and soffit on site.

Haulotte 4527A towable boom or 45XA drivable; Bil-Jax scaffold tower; 32 ft extension ladder; aluminum brake

Backfill, grade and restore the lawn

Backfill the footing trench in lifts and compact it with the plate compactor. Bring the stockpiled topsoil back with the loader, shape the grade to drain away from the slab and the house, and run the 72 in soil conditioner on the T66-2 to pull rocks and leave a seedbed. The dump trailer takes the construction debris. Our cleanup guide covers this phase in detail.

Bobcat T66-2 with bucket and 72 in soil conditioner; plate compactor; 7x14 dump trailer

Planning final site cleanup before landscaping begins

Why the order matters

  • Every phase leaves the site different for the next machine. The loader needs the footprint clear. The excavator needs the pad graded so the footing depths are measured from a known surface. The telehandler needs a firm staging spot that was decided before the footing spoil got piled on it. The boom lift needs outrigger pads on ground that was not just backfilled. If you book machines by phase and walk the site before each delivery, each one arrives to a lot that is ready for it.
  • The two things that most often stall a garage build are the utility locate and the ground. Contact MISS DIG 811 at least three business days before any digging, trenching or augering; it is free and required by Michigan law, and it does not mark private lines such as the run from the house to an existing shed or a landscape lighting circuit. For the ground, tracks spread weight and reduce rutting, but they do not make saturated ground workable. After a hard rain, give it a day before the loader or the telehandler arrives.

When to bring in a professional

  • A detached garage on a slab with a frost footing is within the fleet. A garage with a full basement, a retaining wall holding back a slope, or a footing that has to go deeper than the E35 and E48 reach is a job for a contractor with larger equipment. Setting a heavy steel beam or a long-span girder that lands outside the telehandler's chart at reach is a crane job. Call and describe the lift; we'll tell you if it is one.

Before the first delivery, check the lot.

Measure the lane

The E35 is 69.7 in wide and the T66-2 is 67 in; both need a clear 6 ft plus the turn. The SkyTrak 6034 is 7 ft 11 in wide and arrives on our truck, which needs room to unload. Measure the clear opening and the route, not the nominal gate size.

Plan the staging zones

Spoil pile, topsoil stockpile, lumber drop, truss drop and the telehandler's parking spot all need firm ground that stays clear of the footing backfill and the septic field.

Know the dimensions

Footing depth and width from your plans, slab thickness and stone depth, wall height to the top plate, and the horizontal distance from the telehandler's spot to the far wall.

Before ground disturbance: — arrange utility locating through MISS DIG 811 at least three business days ahead, including private lines where needed. Slope or shore any trench a person enters.

Your garage build checklist

Save these details before you request equipment.

  • Footing depth and width, slab size and stone depth from your plans
  • MISS DIG 811 ticket date and any private lines to locate
  • Narrowest point on the route and turning room
  • Spoil and topsoil stockpile locations
  • Heaviest truss weight and the distance from the telehandler spot to the far wall
  • Ready-mix truck access to the forms, or a buggy route
  • Dates for each phase and who is operating

Let's match the machine to your job.

Tell us what you're working on. Our Hamburg team serves Southeast Michigan, seven days a week.

(810) 231-7368

Explore equipment for this guide

Questions before you rent

Which excavator digs garage footings?

The Bobcat E35 is the usual pick. It digs to about 10 ft at the pin, fits through a 6 ft opening at 69.7 in wide, and its blade backfills the trench afterward. The E48 adds reach and lift, which helps when you are loading a dump trailer all day, but it does not dig meaningfully deeper. The E10 digs about 6 ft and passes a doorway, so it suits a footing run in a spot the E35 cannot reach. Footing depth comes from your building department; the frost line here is about 42 in.

Do I need a telehandler for a one-car garage, or will a loader with forks do?

A loader with 48 in forks lands lumber on grade and onto a low deck. It cannot set trusses over a wall or land bundles on a roof. For trusses, the SkyTrak 6034 with the truss boom is the machine; it hangs each truss from a 15 ft extension so you can set it over the plate. If a framing crew is hand-setting trusses on a small garage, you may only need the loader to stage material. Tell us the wall height and the heaviest truss and we'll say which.

How does delivery work for a multi-phase build?

Each phase is its own delivery and pickup, seven days a week on our trucks, priced by drive time from Hamburg and confirmed at checkout. Loaders and mini excavators run $85 round trip within 45 minutes and $125 at 46 to 75 minutes. Towable booms and scissor lifts are $125 and $200. Telehandlers are delivered on our trucks only at $350 and $450. The E35, T66-2 and SVL65-2 can also be towed on our 16 ft trailer behind a 3/4-ton or larger truck if you'd rather haul.

How long should I rent each machine?

You pay for the time the machine is out, not the hours on the meter, and run hours are unlimited. Rental periods are 1 to 4 hours, 4.5 to 24 hours, one week (3 to 7 days) and four weeks. Most people take the loader for a few days, the excavator for a few days, and the telehandler for the day or two the trusses go up. If a phase runs over, the extra time is prorated, never more than the next full period. We cannot give completion times; they depend on your crew, the soil and the weather.

Can the concrete truck reach the forms, and what if it can't?

Ask the ready-mix dispatcher how close the truck can get, given your drive and the lawn. If it cannot back to the forms, the Canycom tracked buggy carries 2,200 lb of concrete per trip at 35 in wide across lawn, mud or a slope, and the wheeled buggy carries a 16 cu ft tub on firm, level ground. Rinse either one as soon as the last load is placed. For footings and small pours, the towable mixer handles 1.5 to 2 bags per batch.