Planning truss placement: information your equipment provider needs

Seven numbers decide the telehandler. Bring them to the call and the booking takes five minutes.

The seven things we need to hear

Each one rules a machine in or out. Have them written down before you call.

Truss weights and spans. The truss drawings from your plant list every piece and its weight. We need the heaviest single piece, usually a girder or a doubled truss, and the span. The weight is compared with the chart at the reach you need, not with the carriage rating. A 6,000 lb machine is not a 6,000 lb truss setter at 25 ft of reach.

Plate height and set distance. Height from grade to the top plate, and the horizontal distance from where the telehandler can park to the farthest point on the plate where a truss lands. The second number surprises people. Footing backfill, a porch slab, a septic field or a fence often keep the machine ten feet farther out than the drawings suggest. The SkyTrak 6034 reaches 23 ft 2 in forward and 34 ft 5 in up. The 6042 and 8042 reach 29 ft 6 in forward and 42 ft 4 in up.

Ground, overhead lines and the stack. The machine weighs 14,500 to 21,200 lb and needs firm, level footing to lift at full chart. Tell us whether the lot is graded, stoned or fresh fill, and whether there is a slope on the set side. Walk the travel lane and the set looking up for power and service lines. Tell us where the truss bundle will be dropped, because the machine has to pick from the stack and travel to the wall with a truss hanging.

Crew and dates. How many people are on the plates to receive and brace, who is operating, and that they are trained. The day you want the trusses set, and a weather fallback. A truss set in wind is a bad day; tell us if your window is tight and we'll talk through the week rate, which covers 3 to 7 days and gives you room to wait for a calm morning.

The seven things we need to hear

Each one rules a machine in or out. Have them written down before you call.

  • Truss weights and spans. The truss drawings from your plant list every piece and its weight. We need the heaviest single piece, usually a girder or a doubled truss, and the span. The weight is compared with the chart at the reach you need, not with the carriage rating. A 6,000 lb machine is not a 6,000 lb truss setter at 25 ft of reach.
  • Plate height and set distance. Height from grade to the top plate, and the horizontal distance from where the telehandler can park to the farthest point on the plate where a truss lands. The second number surprises people. Footing backfill, a porch slab, a septic field or a fence often keep the machine ten feet farther out than the drawings suggest. The SkyTrak 6034 reaches 23 ft 2 in forward and 34 ft 5 in up. The 6042 and 8042 reach 29 ft 6 in forward and 42 ft 4 in up.
  • Ground, overhead lines and the stack. The machine weighs 14,500 to 21,200 lb and needs firm, level footing to lift at full chart. Tell us whether the lot is graded, stoned or fresh fill, and whether there is a slope on the set side. Walk the travel lane and the set looking up for power and service lines. Tell us where the truss bundle will be dropped, because the machine has to pick from the stack and travel to the wall with a truss hanging.
  • Crew and dates. How many people are on the plates to receive and brace, who is operating, and that they are trained. The day you want the trusses set, and a weather fallback. A truss set in wind is a bad day; tell us if your window is tight and we'll talk through the week rate, which covers 3 to 7 days and gives you room to wait for a calm morning.

How the numbers become a machine

  • Residential trusses on a one-story garage or ranch with the machine parked close: the 6034 with the truss boom. Pole barns, two-story plates and sets where the machine must reach past 23 ft: the 6042. Heavy scissor trusses, long-span pieces and doubled girders where the 6042's chart gets thin at your reach: the 8042. Steel or agricultural sets beyond that: the 10042, booked on a call. For most residential work the 6042 or 8042 is plenty.
  • The truss boom is a 15 ft extension with a hook rated 2,000 lb. It lets you hang the truss and set it over the wall and along the plate. It also moves the load 15 ft farther from the machine and adds its own weight, so the machine's capacity with the truss boom mounted is lower than its capacity on forks. Read the chart with the attachment on. Tag lines on both ends of the truss keep it from spinning in the breeze and keep hands off the load until it is over the plate.
  • If a worker has to be at the plate to nail off and the telehandler is already on site, the safety work platform lifts people and tools for that short task: 1,000 lb, up to 4 people, fall protection worn. For hours of bracing and sheathing, a boom lift is the safer machine. Nobody rides the forks.

Before you book, check the site.

A telehandler arrives on our truck. The truck, the machine and the truss stack all have to fit the lot on the same day.

Measure the set distance

Horizontal distance from the telehandler's parking spot to the farthest truss landing on the plate. Measure from where the machine can actually sit, not from the wall line.

Check the ground

Firm, level, and not fresh backfill. A graded pad or compacted stone on the set side lets the machine work at full chart. Saturated ground is not workable; after a hard rain, give it a day.

Clear the lane

A clear path at least a foot wider than the machine from the unload point to the set, with room to turn with a truss hanging. Look up for lines along the whole lane.

Telehandler widths, weights and reach, from our product pages

Capacities are headline ratings with the boom retracted. The chart in the cab governs every lift, and the truss boom reduces it further. Delivered on our trucks only.

SkyTrak 6034: 34 ft 5 in lift, 23 ft 2 in reach, 14,500 lb — 7 ft 11 in

SkyTrak 6042: 42 ft 4 in lift, 29 ft 6 in reach, 19,100 lb — 7 ft 11 in

SkyTrak 8042: 42 ft 4 in lift, 29 ft 6 in reach, 21,200 lb — 8 ft 3.6 in

Operators must be trained. — Read the chart with the truss boom mounted, use tag lines, keep everyone out from under the load, brace each truss before releasing it, and keep the boom clear of power lines.

Your truss-set checklist

Save these details before you request equipment.

  • Heaviest truss or girder weight and span, from the truss drawings
  • Truss count and the order they set in
  • Height to the top plate
  • Horizontal distance from the machine's parking spot to the farthest set point
  • Ground condition and slope on the set side
  • Overhead lines on the lane and at the set
  • Where the truss bundle will be dropped
  • Crew count, operator, training, set date and weather fallback

Let's match the machine to your job.

Tell us what you're working on. Our Hamburg team serves Southeast Michigan, seven days a week.

(810) 231-7368

Explore equipment for this guide

Questions before you rent

Can you pick the machine over the phone?

Yes, if you bring the numbers: heaviest truss weight, plate height, horizontal set distance, and the ground. With those we can say whether the 6034, 6042 or 8042 covers your farthest and heaviest lift with the truss boom on. Without the weight we can only guess, and we will not guess on a lift. Your truss plant lists piece weights on the drawings; ask them for the heaviest piece before you call.

Does the truss boom lower what the machine can lift?

Yes. The truss boom puts the hook 15 ft farther out than the forks and adds its own weight, so the machine's chart with the truss boom mounted shows lower numbers at every position. The hook itself is rated 2,000 lb, which is a ceiling for the attachment, never a promise from the machine. Read the chart in the cab with the attachment on for the reach you will use. If your heaviest truss lands outside it, go up a machine or move the machine closer.

How does telehandler delivery work?

Telehandlers are delivered and picked up on our trucks only; customer towing is not offered for them. Delivery is priced by drive time from Hamburg: $350 round trip within 45 minutes, $450 at 46 to 75 minutes, and a quote beyond that, confirmed at checkout. We deliver seven days a week. We need a firm, clear spot to unload and a lane to the set. Tell us if the trusses arrive the same day so the truck and the material do not fight for the driveway.

Can my crew go up on the telehandler to nail off?

Only on the safety work platform, which is a rated attachment: 1,000 lb, up to 4 people, with fall protection worn by everyone on it. It is for short tasks when the telehandler is already on site. Nobody rides the forks or the truss boom. For hours of bracing, sheathing or fascia, rent a boom lift; our towable and drivable 45 and 55 ft booms are built to carry people and move with the work. Operators of either machine must be trained.

The trusses set in one day. Do I need a week?

The day rate (1 to 24 hours) covers a one-day set with unlimited run hours. Many builders take the week anyway, because it covers 3 to 7 days and gives room for a wind delay or a late truss delivery, and because the same machine stocks the roof afterward. You pay for the time the machine is out, including weekends. Fuel is billed at our cost. Keep it longer than planned and the extra time is prorated, never more than the next full period.