Sequence the work before you book anything
- Every multi-machine project has stages that depend on each other. You cannot compact base you have not spread, and you cannot spread base into a hole you have not dug. Write the stages in order, then write beside each one what has to be true before it can start: material on site, inspection passed, ground dry, help available.
- The machine list falls out of that. Each stage names one or two machines, and most of them are not needed for the whole project. The trap is renting everything on Friday because it feels simpler, then paying for a compactor that sits in the driveway until Sunday afternoon.
What to rent together and what to split
- Rent together when two machines work the same stage. An excavator digging and a loader carrying spoil away is the classic pair; both machines ride on one truck as a dual-machine load, and the dig goes faster because spoil is not piling up in the way. Attachments rented with a Ward's skid steer are half price, so an auger or grapple added to a loader you already have is usually the right call over a second machine.
- Split when one stage must finish and cure, dry or be inspected before the next begins. Footings poured on day one are not ready for a telehandler setting trusses the same afternoon. A compactor rented the same day as the sod cutter waits through the whole excavation.
- Rental periods help here. The week rate covers 3 to 7 days, so a machine you need Friday through Monday is a week rental whether you use it two days or four. A machine you need for one stage on one day is a day rental. Keep a machine past its period and the extra time is prorated, never more than the next full period. Billing is for time out, with unlimited run hours.
Common planning mistakes
- The most common one is scheduling the machine before the material. A loader with nothing to spread is the most expensive lawn ornament you can rent. Book the stone, the pavers, the posts or the concrete first, and the machine for the day after they land.
- The second is no weather buffer. Tracked machines spread weight, but they do not make saturated ground workable. After a hard rain the yard needs a day. Plan a slack day between the dig and the base, and call us if you need to move a delivery.
- The third is forgetting the finish. The paver saw, the lawn roller, the plate compactor on top of the pavers: these come last and are cheap to hold a day. Put them on the list so you are not making a trip to the counter when you want to be finishing.
A generic stage plan
Most yard and small-structure projects follow this shape. Your supplier's spec and inspector's schedule fill in the dates.
Two machines on one truck is routine for us. A dual-machine load has its own delivery tier, confirmed at checkout. Tell us the whole project at booking and we will tell you which machines should share a truck and which should come later.
Clear what is there
Sod, old concrete, brush or a stump. One machine, one day, often before anything else is delivered.
Sod cutter, demolition hammer, SC30TX stump grinder, root grapple on a loader
Dig to depth
Footings, a patio footprint, a trench. Spoil has to go somewhere; a dump trailer or a loader the same days keeps it moving.
E10, E35 or E48; trencher for narrow runs; MT100 or T66-2 bucket for shallow digs
Bring in base or set material
Base stone, posts, block, pallets. Schedule the machine for the day after the material lands.
MT100 or T66-2 with bucket or forks; Canycom buggy through a 36-inch gate; telehandler for height
Compact in lifts
A few inches at a time, per your supplier's spec. Needs dry material and a dry day.
Plate compactor for pads and patios; 36-inch ride-on roller for driveways
Cut, set, roll
Paver cuts, final compaction with a pad, seed and roll. Short rentals, often the same day you return the compactor.
Paver saw, plate compactor, lawn roller
Check the site once for every machine on the list
The widest machine on your plan sets the access requirement for the whole project.
Measure for the widest machine
If the plan includes an E35 or T66-2, the route needs a clear 6 feet, and the 66-inch grapple or 72-inch soil conditioner can be wider than that. If only the MT100 class fits, every stage has to be planned around it.
Plan the material drop
Stone, pavers and lumber need a spot the delivery truck can reach that does not block the equipment trailer or the route to the work.
Know every stage's dimensions
Dig depth from the plans, square footage and base depth from the supplier, lift height and load weight for anything a telehandler will set.
Before any stage that disturbs ground: — contact MISS DIG 811 at least three business days ahead. It is free and required by Michigan law. It does not mark private lines.
Your project plan checklist
Fill this in before you book the first machine.
- Stages in order, with what must be true before each one starts
- Material delivery dates, booked before the machines
- Which machines share a stage and should share a truck
- Which stages need a cure, dry or inspection gap
- A weather buffer day between dig and base
- Finish tools on the list: saw, roller, compactor pad
- Widest machine measured against the route
Let's match the machine to your job.
Tell us what you're working on. Our Hamburg team serves Southeast Michigan, seven days a week.
(810) 231-7368
Machines that anchor most stage plans
Questions before you rent
Is it cheaper to rent everything for one week or each machine for a day?
It depends on how many days each machine actually works, and we will not quote a savings number here because every project is different. The structure is simple: the week rate covers 3 to 7 days, so any machine you need for three or more days is a week rental. A machine needed for a single stage on a single day is a day rental. Write the stage plan first, count the days per machine, and the answer is usually obvious. Call and we will run the numbers with you.
What does it cost to deliver two machines at once?
A dual-machine load, such as an excavator and a loader on one truck, is priced at its own delivery tier: $125 round trip within 45 minutes of Hamburg and $200 at 46 to 75 minutes, confirmed at checkout. A single truck-and-trailer load is $85 and $125 at the same distances. Beyond 75 minutes we quote by phone. Sometimes two separate deliveries on different days is the right plan anyway, because the second machine is not needed until the first stage is done.
Should I rent a second machine or an attachment?
Start with the attachment. Attachments rented with a Ward's skid steer are half price, and a loader with forks, an auger or a grapple covers several stages without another delivery. A second machine makes sense when two different kinds of work happen at the same time, like digging and hauling spoil. Tell us the stages and we will say which it is.
What if a stage runs long and I need the machine another day?
Call before the period ends. Extra time is prorated, never more than the next full period. If you are already at a week rate, a day or two more is a small add. The bigger risk is the next machine arriving before its stage is ready, so when one stage slips, call about moving the next delivery too.
Where do the existing step-by-step guides fit in?
This guide is about sequencing and scheduling. The paver patio guide lays out seven steps with a machine for each and a typical weekend package of sod cutter, MT100, plate compactor and paver saw. The pole barn guide walks six phases from grading through the floor. Use those for the stage detail and this one to decide what overlaps and what waits.