A small addition, phase by phase
The house is in the way of every machine. Measure the route first, then pick the machines that fit it.
Every machine on this page is picked for a route first and a task second. If your route is a clear 6 ft, swap the E10 for the E35 and the MT100 for the T66-2 and the work moves faster. If it is 36 in, the small machines are the job, and a few inches short means pulling a fence panel rather than renting something that cannot get there.
Open a route and protect what stays
Most additions are reached down a side yard between the house and the lot line, past a gate, a meter and an air conditioner. Measure the narrowest clear opening and the turn into the backyard. A 36 in clear opening passes the MT100 (35.6 in), the Canycom tracked buggy (35 in) and the E10 with its undercarriage retracted to 28 in. A clear 6 ft passes the E35 and the full-size loaders. Lay plywood over soft lawn and over any line you know about. Tracks spread weight and reduce rutting; they do not prevent lawn damage.
Tape measure first; then MT100, E10 or Canycom for a 36 in route, E35 and T66-2 for a 6 ft route
Dig the footings beside the existing foundation
Footings go to the depth your building department requires; plan on the frost line, about 42 in in most of southeast Michigan. The E10 digs about 6 ft, works through a 36 in route and has zero tail swing, so it digs along the house without the counterweight hitting the siding. The E35 digs to about 10 ft and moves soil faster when a 6 ft route exists. Digging next to an existing footing can undermine it; keep the new trench away from the old footing's bearing and ask your building department or an engineer how close you can go. Slope or shore anything a person stands in. Contact MISS DIG 811 at least three business days ahead, and locate private lines (gas grill line, irrigation, landscape lighting, the dryer vent) yourself.
Bobcat E10 for a narrow route; Bobcat E35 for a 6 ft route; E48 only when the job needs more reach and lift
Carry spoil out and stone in
Spoil from a footing trench adds up fast and has to leave through the same narrow route. The MT100 with bucket moves it to a dump trailer at the street, 1,000 lb rated capacity per trip. The Canycom buggy carries 2,200 lb per trip with no loader to operate and dumps straight forward. Bring base stone in the same way. The 7x14 dump trailer holds 10.9 cu yd but fills by weight with wet soil long before it looks full.
Bobcat MT100 with bucket; Canycom tracked buggy; 7x14 dump trailer
Compact, pour and cut
Compact base stone in lifts with the plate compactor; at 194 lb it goes wherever the buggy went. Ready-mix rarely reaches the back of a house, so the tracked buggy carries concrete from the truck to the forms across lawn or a slope. Footings and small pours can come out of the towable mixer at 1.5 to 2 bags a batch. Cut control joints in a slab with the early-entry saw within hours of finishing.
Plate compactor; Canycom tracked buggy; concrete mixer; early-entry saw
Set the roof and tie into the house
A one-story addition's trusses or rafters are within the SkyTrak 6034's 34 ft lift and 23 ft forward reach, if the telehandler can park where it reaches the set. It is 7 ft 11 in wide and arrives on our truck, so on many lots it works from the driveway or the street side only. When it cannot reach, a framing crew hand-sets and the loader forks stage lumber at grade. For the siding and roof tie-in, a towable 45 ft boom reaches the eave from the lawn with outriggers on pads; a Bil-Jax tower suits hours of flashing work in one spot.
SkyTrak 6034 with forks and truss boom; Haulotte 4527A towable boom; Bil-Jax scaffold tower; 32 ft extension ladder
Close it in and finish
Once the shell is weathertight, the Panellift drywall lift holds sheets up to 4 x 16 ft at 14 ft 5 in for ceilings, and a Baker rolling scaffold moves room to room under ceilings below about 12 ft. In cold weather, the 75,000 BTU forced-air heater warms a sealed-off addition under construction; it burns fuel in the space, needs ventilation, is never used in a living space, and a CO detector is suggested. Keep it on the construction side of the sealed opening. Fans move air to dry mud and paint.
Panellift drywall lift; Baker 6 ft scaffold; 75,000 BTU forced-air heater; 24 in floor fan
Working against an occupied house
- An addition touches a building people are living in. That changes three things. First, the services: the gas line, the water service, the sewer lateral and the electric feed all enter the house somewhere, and an addition often lands on top of one. MISS DIG marks public utilities to the meter; everything past it is yours to find. Second, the foundation: the new footing sits beside the old one, and the soil under the old footing has to stay put. Third, the opening: the wall you cut into becomes a hole in a lived-in house until the shell is sealed, so sequence the cut-through late and the weathertight shell early.
- Small excavators earn their place here. The E10's zero tail swing means the back of the machine stays inside its tracks as it swings, so it can work tight to the siding. The E35 also has zero tail swing with more reach and dig speed, when the route allows it. Neither one is the right tool for a full basement under an addition or for underpinning an existing foundation; those are contractor jobs with engineering behind them.
Before the first delivery, check the route.
Measure the narrowest point
Clear opening with the gate fully open, including latch hardware, the meter, the AC unit and the turn. A bucket on the MT100 is machine width; the soil conditioner is wider and will not pass a 36 in gate.
Walk the route
Septic tank and field, irrigation heads, the sewer cleanout, window wells and any downspout drain. Plywood over soft lawn; a day's wait after hard rain.
Know the dimensions
Footing depth and width, distance from the new footing to the old one, slab thickness and stone depth, and the height to the tie-in at the eave.
Machine widths, from our product pages
Width is the machine body. Add the attachment and a few inches each side before you call it a fit, and measure the turn into the opening, not just the opening.
Bobcat E10 mini excavator — 28 in retracted / 43 in extended
Canycom tracked buggy — 35 in
Bobcat MT100 stand-on loader — 35.6 in
Bobcat T66-2 track loader — 67 in
Bobcat E35 mini excavator — 69.7 in
SkyTrak 6034 telehandler — 7 ft 11 in
Before ground disturbance: — arrange utility locating through MISS DIG 811 at least three business days ahead. Find your own private lines. Slope or shore any trench a person enters.
Your addition checklist
Save these details before you request equipment.
- Narrowest clear opening on the route and the turn into it
- Footing depth and width, and the distance to the existing footing
- MISS DIG 811 ticket date; private lines you have located
- Where spoil goes out and where stone and concrete come in
- Ready-mix truck access, or a buggy route
- Eave height at the tie-in and where a lift or ladder can set
- Dates for each phase and who is operating
Let's match the machine to your job.
Tell us what you're working on. Our Hamburg team serves Southeast Michigan, seven days a week.
(810) 231-7368
Explore equipment for this guide
Questions before you rent
My side yard is 38 inches between the house and the fence. What gets through?
Measure the clear opening at the tightest point with everything in the way counted: the gate latch, the meter, the AC pad. At a true 36 in clear, the E10 (28 in retracted), the Canycom buggy (35 in) and the MT100 (35.6 in) can pass when the turn allows it. The MT100's bucket is machine width, but other attachments are wider. Width is only half the question; also check the turn at each end and what the tracks will cross. If you're a couple of inches short, pulling one fence panel is usually easier than running the whole job on hand tools.
E10 or E35 for addition footings?
The route decides. The E10 digs about 6 ft, passes a doorway-width gap and has zero tail swing, so it works tight to the house. The E35 digs to about 10 ft, moves soil faster and loads a trailer, but needs a clear 6 ft to get there. Both reach the ~42 in frost line with room to spare. The E48 adds reach and lift, not depth, and needs an even wider route, so it is rarely the addition machine. Call with your route width and we'll confirm.
How do I get concrete to the back of the house?
Ask the ready-mix dispatcher how far the truck can get down your drive. For the rest of the distance, the Canycom tracked buggy carries 2,200 lb per trip at 35 in wide across lawn, mud or a slope and dumps straight forward into the forms. The wheeled buggy carries a 16 cu ft tub on firm, level ground. For footings alone, the towable mixer at 1.5 to 2 bags per batch may be enough. Rinse the buggy or mixer as soon as the last load is placed.
Can I heat the addition while I finish it?
Once it is sealed off from the occupied house, yes. The 75,000 BTU forced-air heater is sized for garages and additions. It burns kerosene, diesel or fuel oil in the space, so it needs ventilation, is never used in a living space, and a CO detector is suggested. Refuel only when it is off and cool. Keep it on the construction side of the sealed opening, not in the rooms people are living in. Our winter heating guide covers sizing.
Delivery or tow it myself?
The E10 and MT100 ride on our trailers, and a half-ton pickup typically handles the MT100 on the 12 ft ramp trailer with a 2 in ball; we confirm your setup at the counter. The E35 needs a 3/4-ton truck and the 16 ft trailer with a 2 5/16 in ball. Delivery runs seven days a week on our trucks, priced by drive time from Hamburg: $85 round trip within 45 minutes for a loader or mini excavator, $125 at 46 to 75 minutes, and a quote beyond that. Telehandlers are delivered only, at $350 and $450. The fee is confirmed at checkout.