Three families, three kinds of day
- Excavation machines (the E10, E35 and E48, the trencher) do their work early and leave. Material handling machines (the T66-2 and SVL65-2 with bucket, forks or grapple, the MT100, the buggies, the dump trailer, the telehandlers) show up at the start and keep coming back. Access machines (towable and drivable booms, scissor lifts, scaffold towers) arrive after the shell is up. A build goes wrong on equipment when a machine from one family sits idle through another family's phase, or when the next machine arrives to a lot the last one left unready.
- The rental periods make sequencing easy to price. Everything rents by the half day (1 to 4 hours), the day (4.5 to 24 hours), the week and four weeks, with unlimited run hours. The week rate covers 3 to 7 days, so a phase that runs Thursday through Monday is one week, and a 4-week rate is much cheaper per day for a machine that stays the whole build. Fuel is billed at our cost. If a phase runs over, the extra time is prorated, never more than the next full period.
A typical sequence and the handoff at each step
Durations depend on your crew, the soil and the weather. The order and the handoffs do not.
- Phase 1, clearing and rough grade: T66-2 or SVL65-2 with bucket and the 66 in grapple; dump trailer for brush and spoil. Handoff: footprint stripped, topsoil stockpiled out of the way, a firm spot marked for the telehandler later. MISS DIG 811 ticket in hand at least three business days before any digging.
- Phase 2, excavation: E35 (E48 for more reach and lift; E10 for narrow access), trencher for shallow narrow utility runs. Keep the loader if spoil has to move far or a trailer has to be loaded all day. Handoff: footings and trenches dug and inspected, spoil where the next machines do not need to drive, trenches a person enters sloped or shored.
- Phase 3, base and concrete: plate compactor or ride-on roller, mixer or tracked buggy, early-entry saw. The excavator can go home. Handoff: slab or footings cured enough to work from, buggy route cleaned up.
- Phase 4, framing: telehandler with forks and truss boom, delivered on our truck, usually for a few days around the truss set and roof stocking. The loader with forks stages ground-level material. Handoff: staging pad firm, truss stack placed where the machine picks from it, overhead lines checked.
- Phase 5, exterior: towable or drivable boom for siding, roofing and trim; scaffold tower or extension ladder for a single spot; aluminum brake for trim coil. The telehandler can go home. Handoff: outrigger pads on firm ground, lane along the building kept clear.
- Phase 6, final grade and cleanup: loader returns with bucket and the 72 in soil conditioner; plate compactor for trench backfill; dump trailer for debris. Handoff: everything else off the lot, topsoil stockpile accessible.
Where the overlaps are worth paying for
- The loader is the machine most worth keeping. It clears, moves spoil beside the excavator, stages pallets for the framers and does the final grade. If you need it in four of six phases, a four-week rental beats four separate week rentals and four deliveries. The excavator and the telehandler are the opposite: expensive to deliver and useful for a short window, so book them tight to the phase and have the lot ready when the truck arrives.
- Two machines on one delivery is routine for us. A mini excavator and a loader ride the same truck as a dual-machine load, at its own delivery tier, confirmed at checkout. Telehandlers always travel alone on our trucks. If you have a 3/4-ton or larger truck, the loaders and the E35 can also go home on our 16 ft trailer, which gives you more control over timing than waiting for a delivery slot in peak season.
Before each delivery, check the lot.
Each machine family needs a different kind of ready.
Excavation: route and locates
Clear 6 ft for the E35 and loaders, 36 in for the E10 and MT100, measured at the clear opening and the turn. MISS DIG ticket active. Private lines located by you.
Material handling: staging and ground
Firm, level pads for pallets and for the telehandler, off the backfill and the septic field. Tracks spread weight and reduce rutting; they do not make saturated ground workable. After a hard rain, give it a day.
Access: footing and the lane up
Towable booms set outriggers on firm ground or pads; scissors need a slab, not lawn; scaffold towers need level ground and leveling jacks. A clear lane along the building and overhead lines checked.
Machine widths, from our product pages
Width is the machine body. Attachments can be wider, and the pallet on the forks usually is. Measure the clear opening and the route before each delivery, not once at the start.
Bobcat E10 mini excavator — 28 in retracted / 43 in extended
Bobcat MT100 stand-on loader — 35.6 in
Bobcat T66-2 track loader — 67 in
Bobcat E35 mini excavator — 69.7 in
Bobcat E48 mini excavator — 72.8 in
SkyTrak 6042 telehandler — 7 ft 11 in
Before ground disturbance: — arrange utility locating through MISS DIG 811 at least three business days ahead, including private lines where needed. Slope or shore anything a person stands in.
Your phase-planning checklist
Save these details before you request equipment.
- Phase list with target dates and the machine family for each
- Which machines overlap, and which one stays the whole build
- MISS DIG 811 ticket date
- Narrowest opening and route, re-checked before each delivery
- Staging pads: spoil, topsoil, pallets, telehandler, lift outriggers
- Delivery or tow for each machine, and your truck's rating
- Who operates each machine, and their training
Let's match the machine to your job.
Tell us what you're working on. Our Hamburg team serves Southeast Michigan, seven days a week.
(810) 231-7368
Explore equipment for this guide
Questions before you rent
Should I book the whole build at once?
Book the first phase firmly and tell us the rest of the plan. We'll pencil the later machines against your dates so a telehandler is available when the trusses come, and you confirm each one as the phase gets close. Builds slip, and a machine booked three weeks early for a date that moves helps nobody. In the busy season, the earlier we know, the better the odds of your preferred day.
Can two machines come on one delivery?
Yes. A mini excavator and a loader ride together as a dual-machine load. We deliver seven days a week on our trucks, priced by drive time from Hamburg and confirmed at checkout: $85 round trip within 45 minutes for a single truck-trailer load and $125 at 46 to 75 minutes; dual-machine loads, scissor lifts and towable booms are $125 and $200; telehandlers travel alone at $350 and $450. Beyond 75 minutes we quote by phone. You can also tow the E35 and the loaders on our 16 ft trailer with a 3/4-ton or larger truck, and towable booms behind a properly rated pickup.
Week rate or day rate for each phase?
The week rate covers 3 to 7 days, so any phase that runs three days or more is a week. The day rate (4.5 to 24 hours) suits a one-day truss set or a half-day unload. A machine you want through most of the build, usually the loader, is cheaper per day at four weeks than as separate weeks with separate deliveries. Run hours are unlimited; you pay for the time the machine is out, weekends included. Fuel is billed at our cost. Overruns are prorated, never more than the next full period.
Can I swap the excavator for the loader mid-rental?
Call us and we'll arrange the pickup and the next delivery together, often on the same truck trip. Each machine is its own rental, so the excavator's period ends when it leaves and the loader's starts when it arrives. Tell us a day or two ahead in season. If you are not sure whether the next phase needs the E35 or the T66-2 on a given day, keep the loader and send the excavator home; the loader is the one you will reach for most often.
What happens if rain stops the job?
We do not publish a weather or cancellation policy on the site, so call us and talk it through before the delivery day; we're open seven days a week. On the ground side, tracked machines spread weight and reduce rutting, but they do not make saturated ground workable, and a telehandler on soft ground cannot lift at full chart. After a hard rain, give the lot a day. If your window is tight, the week rate gives room to wait for a dry morning without paying for extra days one at a time.